What Is an Inspection and Test Plan (ITP) for a Modular Building? (2026)

An inspection and test plan, or ITP, is the document that lists every check made on a modular building while it is built in the factory, who makes each check, and what record proves it was done. It sets hold points where work stops until an inspector, often the project engineer, has signed off. The signed records are then handed to the building surveyor or certifier as part of the evidence for the building permit and occupancy.

This page is for builders, developers and council project managers in Australia buying modules for the first time, whose building surveyor asks how the hidden work inside each module will be proven.

Why an ITP matters more for modular

Most of a module is closed up before it leaves the factory. Welds, fire stopping, membranes and pipework end up behind linings. The ITP fixes the moment of each inspection in advance, so the right person sees the work while it is still visible.

What a modular ITP usually covers

Hold points in the factory

  • Steel frame: member sizes, welds and bolted connections checked against the structural drawings before any lining.
  • Coatings: surface preparation and coating checked on the frame before it is closed in.
  • Fire and acoustic separation: wall and floor build-ups and penetrations checked before linings go on.
  • Waterproofing: wet area membranes inspected and flood tested before tiling.
  • Services: plumbing pressure tested and electrical rough-in checked before walls are closed.
  • Pre-dispatch: final walk of each finished module, lifting points and transport bracing checked.

Witness and review points

Not every line is a hold point. At witness points the inspector is invited but work can continue; at review points a record is checked later. A good ITP says which is which.

The project engineer in the factory

The structural steel frame is fabricated in an offsite factory and inspected there by the project engineer at the frame hold points. The engineer’s inspection reports become part of the ITP record. National rules on factory QA are still forming; the national certification scheme for MMC manufacturers is targeted for about mid-2028, according to the NCCB. Our note on MMC manufacturer certification and factory QA records explains what that may change.

What EcoPrestige supplies

EcoPrestige supplies engineered structural steel volumetric modules, built and inspected in an offsite factory. With the modules we supply the ITP for your project, the signed inspection records, test results such as pressure and flood tests, and photographs of hidden work at each hold point. These go into the documentation pack your builder hands to the surveyor. See supply-only modular and the documentation pack for how that pack fits a builder’s head contract.

What an ITP does not do

An ITP is a record of checks. It does not approve the building or replace the building surveyor, and it covers only the factory scope. Footings, crane lifts, module connections and services hook-up need their own checks under the builder’s quality system.

The approval path

The building surveyor or certifier decides what evidence is needed and sets the inspection regime. Ask them early whether they accept engineer inspection in the factory, and ask them to set out their full inspection regime, so the ITP is built to it. On modular projects, surveyors commonly inspect the footings on site and carry out the final inspection before occupancy, with frame evidence coming from the factory records where they accept it. EcoPrestige coordinates the module design with your consultants; permit drawings are issued by the registered or licensed practitioner the state requires. In Queensland, permit drawings are issued under a QBCC licensed building designer. In Tasmania, they are issued by a licensed Tasmanian building designer. Our building permit guide for modular buildings covers the surveyor’s side in more detail.

The programme

The ITP is agreed before production. While the factory works through its hold points, the builder prepares the site and footings. Factory and site work run in parallel, so time on site is shorter. Book inspectors ahead, or the factory waits.

What to send us

  • 1. The site address and the building use.
  • 2. Your building surveyor or certifier, if appointed.
  • 3. Their inspection regime or documentation checklist, if they have issued one.
  • 4. Your structural engineer’s details and whether they will attend the factory.
  • 5. Any drawings or a sketch.

Consultants can use our consultant brief for engineers and surveyors to see what we need from them.

ITP questions buyers ask

What is a hold point in a modular ITP?
A hold point is a stage where factory work stops until a named inspector has checked and signed off the work. Common hold points are the steel frame before lining, wet area membranes before tiling and services before walls are closed.

Who inspects the modules in the factory?
The factory quality team checks every line of the ITP. The project engineer inspects the structural steel frame at the frame hold points, and the building surveyor may ask to see other stages.

Does the building surveyor accept factory inspection records?
Many do, but it is their decision. Ask your building surveyor early whether they accept engineer inspection in the factory and what records they want, so the ITP is built to their list.

Does an ITP replace site inspections?
No. The ITP covers the factory work. Footings, module connections and services hook-up on site still need inspection, and the surveyor still carries out the inspections they require before occupancy.

When should the ITP be agreed?
Before the factory starts. Once a wall is lined, the work behind it cannot be inspected without opening it up.

Want the ITP built to your surveyor’s checklist?

Send the site, the use and any drawings to prebuilt@ecoprestige.com.au or download our technical brochures.