A planning permit decides whether a building may be used and placed on a site at all: its use, siting, size and how it sits in its setting. A building permit decides whether it will be built safely to the National Construction Code. A modular building needs planning approval wherever the local scheme requires it, and a permanent modular building always needs building approval.
This page is for homeowners, builders, developers and councils across Australia putting a factory-built building on a site. The problem is that each state uses different names for the same two steps, and many buyers think a factory-built building somehow skips one of them. It does not. Getting the order right is what keeps a modular programme moving.
The plain difference
- Planning: is this use allowed here, and does the building fit the zone, overlays, setbacks, height and neighbourhood rules? Assessed by the council or a planning authority.
- Building: is the structure, fire safety, energy, wet areas and access compliant with the NCC? Assessed by a building surveyor or certifier.
- Planning normally comes first. Building approval follows, then inspections, then a final certificate before use.
Our page on what a town planner needs for a modular building covers the planning stage.
The approvals by name in each state
Names below are the common ones; always confirm with your building surveyor or certifier and the council.
- Victoria: a planning permit from the council where the scheme requires one, and a building permit from a registered building surveyor. A small second dwelling up to 80 m2 usually needs no planning permit (VC253, updated by VC306 in October 2026), but a building permit is always needed. An occupancy permit or certificate of final inspection closes the job.
- New South Wales: development consent through a development application, or a complying development certificate where the project meets set standards. Then a construction certificate from a registered certifier, and an occupation certificate at the end.
- Queensland: a development approval where the planning scheme requires one, for example for a material change of use. Building approval comes from a QBCC-licensed building certifier.
- Western Australia: development approval from the local government where required. A building permit is then issued by the permit authority, supported by certification from a registered building surveying contractor.
- South Australia: planning consent and building consent, which together form development approval under the Planning, Development and Infrastructure Act. Certification can be by an accredited professional.
- Tasmania: a planning permit from the council where the scheme requires one, and a building permit, with a licensed building surveyor certifying the building work.
- ACT: development approval where required, and building approval, with a licensed building surveyor certifying.
- Northern Territory: a development permit where the planning scheme requires one, and a building permit from a registered Building Certifier.
Why modular fits this sequence
A modular building can be designed and lodged for planning at the same time as the module design is coordinated. Once planning is through, building approval documents draw on module details that are already set. If you already hold a planning permit for a site-built design, our page on converting an approved design to modular explains what has to change.
Who designs and who certifies
For homes in Victoria, design, permit documentation and construction are contracted by our sister company DST Project Management and Construction Pty Ltd, registered domestic builder CDB-U 72187. In Queensland, permit drawings are issued under a QBCC licensed building designer. In Tasmania, permit drawings are issued by a licensed Tasmanian building designer. For commercial projects in NSW, WA, SA, the ACT and the NT, EcoPrestige coordinates the module design with your consultants; permit drawings are issued by the registered or licensed practitioner the state requires. The building surveyor or certifier certifies.
What EcoPrestige supplies
EcoPrestige supplies engineered structural steel volumetric modules, built and inspected in an offsite factory, with the module drawings and engineering inputs your consultants need for each approval.
What does not fit
Do not order modules before planning approval is in hand, unless you accept the risk of changes. And a modular building is not exempt from approvals because it is made in a factory.
The programme
Planning, then building approval, then the factory builds while the builder prepares the site. Factory and site work run in parallel, so time on site is shorter. Checking the site before you buy helps too; see our feasibility guide.
What to send us
- 1. The site address and state.
- 2. The use and the size of the building.
- 3. Any planning permit or consent already issued.
- 4. Any drawings or a sketch.
Planning and building permits: questions buyers ask
What is the difference between a planning permit and a building permit?
A planning permit decides whether a building may be used and placed on a site. A building permit decides whether it is built safely to the National Construction Code. Most projects need both.
Does a modular building need a planning permit?
It needs planning approval wherever the local planning scheme requires one, exactly as a site-built building would. Some small buildings are exempt in some states.
Does a modular building need a building permit?
Yes. A permanent modular building needs a building permit or approval like any other building of its class.
Does a granny flat in Victoria need a planning permit?
A small second dwelling up to 80 m2 usually needs no planning permit in Victoria (VC253, updated by VC306 in October 2026), but a building permit is always needed.
What is a building permit called in NSW?
In NSW the building approval is a construction certificate, or a complying development certificate where the project meets set standards. A registered certifier issues it.
Related: our guide to AS 3740 wet area waterproofing. | small second dwelling Victoria now 80 m2
More detail: modular construction in Canberra.