On a modular factory visit, check the work you will never see again once the modules are closed: the steel frame and welds, the coatings, the wet area waterproofing, the services before walls are lined, and the fire and acoustic separation. Then check the paperwork, because the inspection and test plan and its signed records are what your building surveyor relies on. A tidy factory floor matters less than whether each module can be traced to its records.
This page is for builders, developers, councils, engineers and owner’s representatives in Australia who are about to visit a module factory before or during production. The problem is that a visit can turn into a tour of the showroom module, when the real value is in the work stations and the quality records.
Why a factory visit matters
With modules, most of the building is made before the site sees it. A visit lets you, your engineer or your surveyor see the work while it is open and check that the factory is building to the approved drawings. It is also the best time to agree how hold points will be inspected for your project.
The checklist
Welding and steel
- Member sizes and steel grades match the structural drawings.
- Welds are complete, even and free of obvious defects, with a weld inspection record.
- Bolted connections, lifting points and module-to-module connection plates are as drawn.
- Steel material certificates can be traced to the frames.
Coatings
- Surface preparation before coating, and coating type as specified.
- Coating thickness checks recorded.
- Damaged coating touched up before closing in.
Waterproofing
- Wet area membranes installed to the specified system, with upturns and set-downs.
- Flood tests carried out and recorded before tiling.
- Roof and external wall weatherproofing details, including how the site joins will be sealed.
Services
- Plumbing pressure tested and recorded before walls close.
- Electrical rough-in checked, with cables protected through steel.
- Connection points at module edges labelled for site hook-up.
Fire and acoustic separation
- Wall and floor build-ups match the fire and acoustic design.
- Penetrations through rated walls are sealed with the specified system.
Records and the ITP
- An inspection and test plan for your project, with hold points named.
- Signed records for each module, with photos of hidden work.
- Non-conformances recorded and closed out.
- Finished modules protected, stored and braced for transport.
What EcoPrestige supplies
EcoPrestige supplies engineered structural steel volumetric modules, built and inspected in an offsite factory. The structural steel frame is inspected in the factory by the project engineer at the frame hold points, and the records go into the documentation pack. We arrange factory visits for buyers and their consultants on request. For more on records, see MMC manufacturer certification and factory QA records.
What a visit cannot tell you
One visit shows the factory on one day. It does not prove every module will be built the same way. That is the job of the inspection and test plan, the hold points and the records. A visit also cannot replace your own due diligence on the supplier: references, prior jobs and the scope documents. Our page on how to evaluate a modular supplier covers the rest.
The approval path
The building surveyor or certifier decides what factory evidence they accept. Ask whether they accept engineer inspection in the factory and what their full inspection regime is. The national certification scheme for MMC manufacturers is targeted for about mid-2028, according to the NCCB, so for now the surveyor’s checklist is the standard. EcoPrestige coordinates the module design with your consultants; permit drawings are issued by the registered or licensed practitioner the state requires. In Queensland, permit drawings are issued under a QBCC licensed building designer. In Tasmania, they are issued by a licensed Tasmanian building designer.
The programme
Plan the visit when your project’s frames and wet areas are open, not after they are closed. The site keeps moving while you visit: factory and site work run in parallel, so time on site is shorter.
What to send us
- 1. Who will visit: you, your engineer, your surveyor or your client.
- 2. Your project and the modules you want to see.
- 3. The stage you want to inspect, such as frame or wet areas.
- 4. Your surveyor’s checklist, if you have it.
Engineers and surveyors can see what we need from them in the consultant brief.
Factory visit questions
What should I check on a modular factory visit?
The steel frame and welds, coatings, wet area waterproofing, services before walls close, fire and acoustic separation, and the inspection and test plan with its signed records.
When is the best time to visit a modular factory?
When your project’s frames and wet areas are still open, so hidden work can be seen before it is lined.
Should my engineer visit the factory?
Yes, where possible. The project engineer inspecting the structural steel frame at the frame hold points gives your building surveyor direct evidence of the hidden structure.
What records should a modular factory keep?
An inspection and test plan, signed hold point records for each module, test results such as pressure and flood tests, material certificates, photos of hidden work and closed non-conformances.
Is a factory visit enough to choose a supplier?
No. It shows one day. Check references, prior jobs, the scope documents and the records system as well.