What Are the Stages of a Modular Building, From Enquiry to Occupancy? (2026)

A modular building moves through these stages in order: enquiry, feasibility, early contractor involvement stage 1, ECI stage 2, permit, factory production, delivery, installation and occupancy. The design must be fixed and approved before the factory starts, because changes are hard once modules are built. Site work runs alongside the factory, so the stages overlap on the ground even though the decisions follow one after another.

This page is for developers, councils, operators and builders in Australia planning a first modular project. The common problem is starting the conversation at the factory stage, with drawings that were never set up for modules, and then losing time redrawing.

Why the order matters for modular

On a site-built job, some design decisions can be left until the walls go up. With modules, the factory needs a frozen design to build from. Each stage below exists to fix one set of decisions before the next stage depends on it.

The stages in order

Enquiry

You send the site, the use and any drawings. We confirm whether modular suits the project in principle and what information is missing.

Feasibility

The site is checked for access, crane position, services and planning controls. This is the moment to find out whether modules can reach the site at all. See modular feasibility before site acquisition.

ECI stage 1

Early contractor involvement stage 1 sets the module layout, the structural system and the indicative scope, so the project can be priced and the consultants briefed.

ECI stage 2

Stage 2 develops the module design with your consultants to the level needed for the permit and for production. The ECI service page explains both stages.

Permit

The building permit or approval is issued by the building surveyor or certifier, and any planning permit by the council. The inspection regime is agreed here, including whether factory inspection by the engineer is accepted.

Factory production

Modules are fabricated and fitted out in the offsite factory against the inspection and test plan, with hold points for the frame, waterproofing and services.

Delivery

Finished modules are wrapped, braced and trucked to site, with any oversize load permits and escorts in place.

Installation

The modules are lifted onto the footings, connected, weatherproofed at the joins and hooked up to services.

Occupancy

The building surveyor carries out the final inspection, reviews the records and issues the occupancy permit or certificate.

What EcoPrestige supplies

EcoPrestige supplies engineered structural steel volumetric modules, built and inspected in an offsite factory. We take part from enquiry through ECI, production and delivery, and supply the records the surveyor needs at occupancy. The builder carries the head contract and the site.

Where the stages break down

Skipping feasibility is the most common failure. So is going to permit on drawings that were not set up for modules, then changing them in production. Late changes to room layouts, window positions or wet areas after the factory starts cause the most cost and delay. Modular is also a poor fit where the design is still moving.

The approval path

The permit stage depends on the state and the NCC class. EcoPrestige coordinates the module design with your consultants; permit drawings are issued by the registered or licensed practitioner the state requires. In Queensland, permit drawings are issued under a QBCC licensed building designer. In Tasmania, they are issued by a licensed Tasmanian building designer. For homes in Victoria, design, permit documentation and construction are contracted by our sister company DST Project Management and Construction Pty Ltd, registered domestic builder CDB-U 72187. Read our building permit guide for modular buildings for the surveyor’s role from permit to occupancy.

The programme

The decision stages run in order, but delivery is not a single line. Once the permit is issued, the factory builds the modules while the builder does the site works and footings. Factory and site work run in parallel, so time on site is shorter. The length of each stage depends on the project, so we give a programme once the scope is known.

What to send us

  • 1. The site address.
  • 2. What the building is for.
  • 3. Any drawings, sketches or a planning permit.
  • 4. Your target occupancy date.
  • 5. Who is on the project team so far.

Modular stages: buyer questions

What are the stages of a modular building project?
Enquiry, feasibility, ECI stage 1, ECI stage 2, permit, factory production, delivery, installation and occupancy, in that order.

When does the factory start building the modules?
After the design is fixed and the building permit or approval is issued, so the modules are built to approved drawings.

What is ECI in modular construction?
Early contractor involvement brings the module supplier in before the design is fixed. Stage 1 sets the module layout and indicative scope; stage 2 develops the design with your consultants for permit and production.

Can site work start before the modules arrive?
Yes. The builder prepares the site, footings and services while the factory builds, which is why time on site is shorter.

Who issues the occupancy permit for a modular building?
The building surveyor or certifier, after the final inspection and a review of the records, including the factory inspection records.

Ready to start at the right stage?

Send the site, the use and any drawings to prebuilt@ecoprestige.com.au or download our technical brochures.